IPSAS 19
Provisions, Contingent Liabilities and Contingent Assets
Prescribes the recognition, measurement and disclosure of provisions, contingent liabilities and contingent assets, including the present-value measurement, reimbursements, restructuring and onerous-contract treatment. Effective 1 January 2004.
IPSAS 19 Provisions, Contingent Liabilities and Contingent Assets is the current, active standard issued by the IPSASB for recognising, measuring and disclosing provisions, contingent liabilities and contingent assets. It is effective for annual financial statements covering periods beginning on or after 1 January 2004 (earlier application encouraged).
IPSAS 19 is based on IAS 37 Provisions, Contingent Liabilities and Contingent Assets, adapted for the public sector with commentary on the broader public-sector obligation concept, onerous-contract and future-operating-deficit treatment, and reimbursements.
Objective, Scope & Exclusions (paras. 1–17)
Definitions (para. 18)
Provisions vs Other Liabilities & the Provision/Contingency Relationship (paras. 19–21)
Recognition – Present Obligation & Past Event (paras. 22–34)
Contingent Liabilities & Contingent Assets (paras. 35–43)
Measurement – Best Estimate (paras. 44–49)
Risks & Uncertainties, Present Value, Future Events, Expected Disposal of Assets (paras. 50–62)
Reimbursements & Changes in Provisions (paras. 63–72)
Future Operating Net Deficits & Onerous Contracts (paras. 73–80)
Restructuring Provisions (paras. 81–96)
Disclosure Requirements (paras. 97–108)
Worked Example – Present Value of a Provision (Illustrative Example IE1–IE2)
Effective Date & Amendment Timeline (paras. 109–112)
Relationship to IAS/IFRS – Comparison with IAS 37
Statement / Process Mapping
- Is there a present obligation from a past event, with no realistic alternative to settling it? If NO → no liability at all
- Is settlement PROBABLE (more likely than not) AND reliably estimable? → recognize a PROVISION (§4, §6)
- Is a present obligation POSSIBLE but not probable, or probable but NOT reliably measurable? → disclose a CONTINGENT LIABILITY, unless remote (§5)
- Is there a POSSIBLE asset dependent on uncertain future events outside the entity's control? → disclose a CONTINGENT ASSET if inflow is probable; never recognize (§5)
- Is the contract ONEROUS (unavoidable costs exceed expected benefits)? → recognize a provision net of recoveries (§9)
- Is there a detailed, communicated RESTRUCTURING plan? → constructive obligation; provision limited to direct, restructuring-specific costs (§10)