IPSAS 11
Construction Contracts
Prescribes the accounting for construction contract costs and revenue – including the percentage-of-completion method, contract cost inclusions/exclusions, the immediate-expected-deficit rule (limited to full-cost-recovery contracts), and the treatment of commercial versus non-commercial public-sector contracts. Effective 1 July 2002.
IPSAS 11 Construction Contracts is the current, active standard issued by the IPSASB for accounting for the costs and revenue of construction contracts. It is effective for annual financial statements covering periods beginning on or after 1 July 2002 (earlier application encouraged). The immediate-expected-deficit rule applies only to full-cost-recovery contracts.
IPSAS 11 is drawn primarily from IAS 11 Construction Contracts, adapted for the public sector with commentary on binding arrangements, cost-plus and non-commercial contracts, and an explicit scope covering contracts with no contract revenue. Unlike the private sector (where IAS 11 was replaced by IFRS 15), IPSAS 11 remains construction-contract-specific, pending IPSAS 47.
Objective, Scope & Definitions (paras. 1–11)
Combining & Segmenting Construction Contracts (paras. 12–15)
Contract Revenue (paras. 16–22)
Contract Costs (paras. 23–29)
Recognition – Percentage of Completion Method (paras. 30–43)
Recognition of Expected Deficits (paras. 44–48)
Changes in Estimates & Disclosure (paras. 49–56)
Worked Example – Noncommercial Aid-Funded Contract (IG9–IG14)
Year 2: Cumulative revenue = 4,100 × 74% = 3,034 (less 1,040 recognized in Yr1 = 1,994 recognized this year); cumulative expenses = 8,200 × 74% = 6,068 (less 2,093 = 3,975 this year).
Year 3: Cumulative revenue = 4,100 × 100% = 4,100 (less 3,034 = 1,066 this year); cumulative expenses = 8,200 (less 6,068 = 2,132 this year).
Worked Example – Commercial Fixed-Price Contract (IG15–IG21)
Year 2: Total revenue 9,200 (incl. variation), total costs 8,200, stage 74% → cumulative revenue 6,808 (less 2,340 = 4,468 this year); cumulative expenses 6,068 (less 2,093 = 3,975 this year); Surplus this year 493.
Year 3: Stage 100% → cumulative revenue 9,200 (less 6,808 = 2,392 this year); cumulative expenses 8,200 (less 6,068 = 2,132 this year); Surplus this year 260. Total surplus over the contract = 1,000.
Effective Date & Amendment Timeline (paras. 57–58)
Relationship to IAS/IFRS – Comparison with IAS 11
Statement / Process Mapping
- Is this a single contract, or should it be COMBINED/SEGMENTED per §2's tests?
- Is the outcome reliably estimable (fixed-price para. 31 tests, or cost-plus para. 32 tests)? If yes → recognize by STAGE OF COMPLETION (§5)
- If not reliably estimable → revenue limited to recoverable costs incurred; no surplus recognized (§5)
- Was the contract intended, at inception, for FULL cost recovery? If yes AND a deficit becomes probable → recognize the WHOLE expected deficit immediately (§6)
- Do estimates change as the contract progresses? → treat as a change in accounting ESTIMATE (IPSAS 3), applied prospectively (§7)